*REVISED*Tangerine Road Phase 2A Widening Project – Traffic Lane Shift

  • Completion DateApril 15, 2026
Tangerine Traffic Lane shift map

UPDATE 4/14/2026: The median construction work on Tangerine Road just east of the Maverik gas station has been extended again. Borderland anticipates completing the work by Tuesday, April 14, 2026.


UPDATE 4/10/2026: Borderland’s anticipated scheduled to complete the median work just east of the Maverick gas station has been extended until Monday, April 13.

A lane shift will be in place while construction crews are at work. Westbound traffic will be reduced to the outside lane only through the work zone. Once work is complete for the day the traffic control devices will get picked up.

For your safety and that of the contractor’s personnel, please comply with traffic control devices, and/or detour signs. If inclement weather or other events cause delays, the work may be rescheduled without further notice.

Hours of Operation for Traffic Lane Change: 6 am to 2 pm


 

REVISED DATE: On Thursday April 9th, Borderland will have a crew working in the median just east of the Maverick gas station. Westbound traffic will be reduced to the outside lane only through the work zone. Once work is complete for the day the traffic control devices will get picked up. Please be aware of traffic control during this time.


On Tuesday April 7th, Borderland will have a crew working in the median just east of the Maverick gas station. Westbound traffic will be reduced to the outside lane only through the work zone. Once work is complete for the day the traffic control devices will get picked up. Please be aware of traffic control during this time.

For your safety and that of the contractor’s personnel, please comply with traffic control devices, and/or detour signs. If inclement weather or other events cause delays, the work may be rescheduled without further notice.

Hours of Operation for Traffic Lane Change: 6 am to 2 pm

This traffic alert is part of a series of communications for this project. Visit Tangerine Road and Interchange Improvements project page for more information.

Great Tangerine Squeeze, Sour now, Sweet Later

Contact details

Matt Everson – Project Engineer
(520) 527-9379